Milestones

09.2017
 

Location decision

04.2018
 

Groundbreaking ceremony

07.2018
 

Awarding of contracts for technological plant construction of melting area to SMS group

4. Quater 2018
 

Awarding of contracts for plants casting and hall construction

4. Quater 2018
 

Start construction of the hall

From 2019
 

Installation of the aggregates

End 2020
 

Start of cold commissioning

2023
 

Production start