Milestones

09.2017
 

Location decision

04.2018
 

Groundbreaking ceremony

07.2018
 

Awarding of contracts for technological plant construction of melting area to SMS group

4th quarter 2018
 

Awarding of contracts for plants casting and hall construction

4th quarter 2018
 

Start construction of the hall

From 2019
 

Installation of the aggregates

End of 2020
 

Start of cold commissioning

2021
 

Production start